1、南侧墙面原有涂料铲除,重新满刮腻子两遍,室外乳胶漆两遍1300.33㎡:
1-17轴南立面:68.23×15.35-(3×2.1×8+2.1×2.1×5)×4
17(2-1)-(2-17)轴南立面:47.51×15.35-(1.8×2.1×13-2.4×2.1+1.2×2.1)×4
2、北侧及东、西山墙原有墙面涂料铲除,重新做真石漆面层1854.07㎡:
A-D轴山墙:10.76×15.35
1-17轴北立面:(68.23+3.6×2)×15.35-(2.4×2.1×6+1.8×2.1×5+1.5×1.8+1.5×2.1)×4
17(2-1)-(2-17)轴北立面:(47.51+4.19)×15.35-(1.2×1.8+1.5×2.1×9+1.2×2.1×5)×4
A)-(2-D)轴山墙:8.46×15.35
3、南侧墙面三道腰线造型原有涂料铲除,重新满刮腻子两遍,室外乳胶漆两遍
(68.23+47.51)×(0.45×2+0.4+0.45×2+0.44)=305.55㎡;
4、北侧及东、西山墙三道腰线造型原有墙面涂料铲除,重新做真石漆面层
(10.76+8.46+68.23+3.6×2+47.51+4.19)×(0.45×2+0.4+0.45×2+0.44)=386.36㎡;
5、南侧窗口造型侧面及窗套原有涂料铲除,重新满刮腻子两遍,室外乳胶漆两遍2.04×8+7.9×8+1.68×5+6.82×5+1.56×13+6.46×13+1.8+7.18+1.32+3.1+4.75×4+4.28×12+5.59×6=343.58㎡;
6、北侧及东、西山墙窗口造型侧面及窗套原有墙面涂料铲除,重新做真石漆面层1.8×6+7.18×6+1.58×5+6.46×5+1.32+5.74+1.44+6.1+1.2+5.38+1.44×9+6.1×9+1.32×5+5.74×5+3.93×7+4.14×5+4.99×4=286.59㎡;
7、过道墙面、柱原有墙面涂料铲除,重新做真石漆面层314.34㎡:
过道墙面:9.26×6.1×2-1.5×2.1+10.8×1.5×2
方柱面:0.6×4×6.1×6
圆柱面:0.275×2×3.14×6.1×8
8、北侧门洞处造型线条底面积顶面原有涂料铲除,重新做真石漆面层
11.98×(0.27+0.45)+7.324×(0.26+0.75)=16.02㎡;
9、南侧门洞处造型线条原有涂料铲除,重新满刮腻子两遍,室外乳胶漆两遍
11.98×(0.27+0.45)+7.324×(0.26+0.75)=16.02㎡;
10、北侧雨棚栏板原有涂料铲除,重新做真石漆面层
(3.15+2.3+12+1.5+4.75)×(1.2+0.2+0.2×2)+9×0.3=45.36㎡;
11、南侧雨棚栏板原有涂料铲除,重新满刮腻子两遍,室外乳胶漆两遍
(12+4.73×2+10)×(1.2+0.3+0.23×2)=61.66㎡;
12、南楼北立面原有涂料铲除,重新满刮腻子两遍,外墙乳胶漆两遍2038.07㎡
1-4层:(97.2+0.6×2+3×2)×15.15
五层以上:59.4×4.2+18.3×1.2+2.6×1.7×2+0.6×0.5×2+0.43×0.5×2
门窗:-(2.05×2.9×2+4.9×2.9+1.7×1.7×5+1.12×1.7×2+2.6×1.7×50+2×1.7×21
幕墙:21×11.9×2+1×14.4×2+2.07×14.4×2+2.235×12.9×2 造型侧立面:东侧29.65×0.3×2×4+13.35×4×2×0.3+(15.95+13.35)×0.3+16.75×2×0.3×3+(8.98+7.03)×0.3 西侧:30.5×2×0.3×4+13.35×5×2×0.3+(15.95+13.35)×0.3+16.75×2×0.3×3+(8.98+7.03)×0.3 中间:(18.7+17.8)×0.9×2+(17+15.5)×0.3×2+13.5×2×0.3+8.61×0.3×2×3+4.47×0.3×2×5+4.47×0.3+4.9×0.3
门窗口侧面:(2.05+2.9×2)×0.54×2+(4.9+2.9×2)×0.54+(1.7+1.7)×2×0.25×6+(1.12+1.7)×2×0.25×2+(2.6+1.7)×2×0.25×50+(2+1.7)×2×0.25×21
锅炉房:11.5×7.5-(3×0.85+10.5×0.85)+(11.5+11.3+5.2×2+4.35+4.15+9.65+9.45)×0.1
13、墙面砖损毁处拆除墙面,重新粘贴墙面砖3×2=6㎡
14、腰线顶部4mm厚SBC120复合防水两遍(68.23+47.51)×0.65×2=150.46㎡;
15、原有室外亮化灯具拆除,管型灯695套;
16、原有室外亮化导线拆除1435m。